Raglan motorists face weeks of disruption as SH23 repairs continue

Reconstruction, resurfacing and slip repairs are under way along SH23, with stop/go traffic management running around the clock.

By The Waikato Advocate · 12 November 2026 · 2 min read

Share
A two-lane rural highway curving past a roadside settlement with a petrol station and coffee shop, hills in the distance
Photo: File/TWA

Motorists travelling between Hamilton and Raglan are being warned to expect continuing delays as extensive road maintenance takes place along State Highway 23.

NZ Transport Agency Waka Kotahi is undertaking road reconstruction, resurfacing and slip repairs at several locations on the route.

Work near the Greenslade Road intersection began on Monday, 9 November, and is expected to continue until mid-December.

During the reconstruction, stop/go traffic management will operate around the clock, with a temporary 30km/h speed limit remaining in place outside normal working hours.

Drivers are being advised to allow up to ten minutes of additional travel time.

More work along the route

Further work is underway west of Whatawhata, where slip repairs are expected to take approximately four weeks.

Additional overnight resurfacing is planned near Bowman Road during the week beginning 29 November.

The works are intended to improve the resilience and condition of the highway, which provides a vital connection for Raglan residents, businesses and visitors.

NZTA says schedules remain weather-dependent.

Motorists are encouraged to plan ahead, obey temporary speed restrictions and monitor official traffic updates before travelling.

Share

Have a story tip or spotted an error? Contact the newsroom.

Comments

No comments yet — be the first to share your thoughts.

Sign in to join the discussion.

Sign in to comment

More from News